Project Triathlon:
Case Study
Triathlon Case Study

Project Triathlon: Advanced Environmental Control for Confectionery Logistics

Sector: Warehousing & Logistics
Location: Derby, Midlands
Project Type: Multi-Zone Temperature, Humidity & Biosecurity Control for Confectionery Storage and Co-Packing
Executive Summary
Project Triathlon sets a new standard in precision environmental management for the confectionery logistics sector. Jet Environmental delivered a fully integrated solution encompassing temperature, humidity, and pressure (biosecurity) control across four distinct warehouse zones, each with unique operational requirements.
This case study highlights the innovative engineering, operational impact, and strategic value delivered to a major confectionery storage and co-packing facility.
Project Overview
The facility required rigorous control of temperature, humidity, and air pressure to safeguard sensitive confectionery products and ensure optimal working conditions.
Jet Environmental’s bespoke system combines seven balanced JET induction systems, advanced humidity regulation, and pressure management for biosecurity, all orchestrated by a central chilled-water plant and intelligent automation.

Solution Architecture
Multi-Zone Environmental Control

-
Humidity Control: Each zone features dedicated humidity sensors and modulating humidification/dehumidification units, maintaining precise relative humidity (RH) tailored to product and process needs.
-
Pressure (Biosecurity) Control: Pressure differentials are actively managed to prevent cross-contamination. Negative pressure in the Taint Store ensures containment of tainted or returned goods, while positive pressure in storage and co-pack areas protects product integrity.
System Components
-
Balanced JET Induction Systems: High-velocity induction nozzles ensure uniform air distribution, supported by medium velocity ductwork.
-
Air Handling Units (AHUs): Each AHU integrates bag and panel filtration, chilled water cooling coils, modulating gas-fired heaters, humidity control modules, and supply fans with run/standby motors.
-
Chiller Plant: Four R32 air-cooled water chillers with multi-circuit compressors, primary/standby pumps, automatic water treatment, and insulated buffer tank.
-
Automation & Monitoring: A Trend standalone control system (AES Ltd) provides real-time monitoring, automated adjustment, and remote diagnostics for all environmental parameters.
Performance & Impact
-
Year-Round Consistency: Stable temperature and humidity conditions are maintained regardless of external fluctuations, ensuring product quality and staff comfort.
-
Biosecurity Assurance: Pressure management mitigates contamination risks, supporting stringent food safety standards.
-
Energy Efficiency: Modular design and intelligent controls optimize energy use and facilitate future expansion.
-
Operational Excellence: The solution delivers low-maintenance reliability, adaptability, and compliance with industry best practices.
Key Features & Specifications

Conclusion
Jet Environmental Systems’ advanced solution for Project Triathlon sets a new standard in multi-zone environmental control for the confectionery logistics industry due to its scale and complexity.
By integrating temperature, humidity, and biosecurity management, the facility achieves optimal product protection, operational efficiency, and regulatory compliance.
The modular, future-ready design ensures ongoing adaptability and value for stakeholders.
General Information
Project Name: DHL EMG TriathlonLocation: Derby, Midlands
Main Contractor: Winvic Construction Limited
Client: DHL Supply Chain
Sector/Application: Confectionery (New Build)
System Type: Heating & Cooling air distribution via ducted Jet air nozzles and fabric duct.
Completion Date: 20/09/2021
Key Building Metrics
Building Length: 260 m
Building Width: 240 m
Average Height: 31 m
Building Area: 62,400 m²
Building Volume: 1,934,400 m³
Environmental & System Metrics
-
Number of AHUs: 7
-
Total Airflow: 104 m³/s
-
Total Heater Output: 2,025 kW
-
Heating Medium: Indirect gas
-
Total Cooling Duty: 2,444 kW
-
Cooling Medium: CHW (Chilled Water)
-
Plant Location: Both internal and external
-
AHU Manufacturer: Jet AHU
-
Cooling Plant: Daikin
Special Features & Comments
-
System covers: New warehouse, includes fabric sock systems.
Completion & Archive
-
Completion Date: 20/09/2021